Your ERRCS permit expired or the installer walked away. Here is how to finish.
Start by asking the permitting office for the permit status and the full file, then collect everything you paid for: the design, the license holder's consent letter, equipment and any test results. In Florida, a property owner may hire a different licensed contractor to close a building permit, and an expired permit whose work is substantially complete may be closed without a new permit if the local office agrees (F.S. 553.79(16)(a) and (b)). Whether your ERRCS job needs a change of contractor or a new permit is the permitting office's call, so ask before work restarts. The system must still pass an acceptance test before it is accepted (IFC 2021 510.5.4).

First, find out where the permit stands
Call or email the office that issued the permit. Depending on where you are, an ERRCS or BDA permit may be a fire, building or electrical permit, and some places need sign-off from several offices. In Broward County, for example, work may not start until every authority having jurisdiction has signed the permit (BORA ERCES Guidelines, FBC Broward 118.4).
Ask these questions and write down the answers:
- Is the permit active, expired, suspended or closed?
- What was the last inspection, and did it pass?
- Who is the contractor of record on the permit today?
- What exactly does the office need to restart or close the job: a change of contractor form, a new permit, revised plans, or a re-inspection?
- Can you get a copy of the full file: approved plans, inspection results and any correction notices?
Permits generally expire if work does not start, or stops, for a period set by the local building code. The time limits and the paperwork for a new contractor differ by office, so get the answer from your permitting office in writing.
What Florida law says about closing a permit
For building permits, Florida gives owners some options (F.S. 553.79(16)):
| Situation | What the statute allows | Citation |
|---|---|---|
| The original contractor will not finish | The owner may keep the original contractor or hire a different licensed contractor to do the work needed and get the inspections to close the permit | F.S. 553.79(16)(a)1 |
| A new contractor takes over | The new contractor is liable only for its own work, not the original contractor's defects | F.S. 553.79(16)(a)1 |
| The permit expired but the work is substantially complete | The local office may let you close it without a new permit, under the code in effect when the application was received | F.S. 553.79(16)(b) |
"Substantially complete" is decided by the local enforcement agency, not by you or the contractor. A radio system that is installed but never passed its acceptance test is not finished from the fire department's view, so ask how they will treat it.
Collect what you paid for
Even if the installer is gone, the work product often still exists. Ask the old installer in writing, and look through your own email, for:
- The design and plans submitted for the permit, including any as-built drawings. The fire code official may require as-built design documents (IFC 2021 510.4.2.7).
- The license holder's consent letter, if one was issued (47 CFR 90.219(b)(1)(i); F.S. 633.202(18)(d)).
- Any signal test or survey reports, with floor grids.
- Equipment lists and serial numbers for the amplifier, battery and antennas, and who owns any equipment not yet installed.
- Amplifier gain settings. If acceptance records and gain values are lost, the owner must rerun the acceptance test (IFC 2021 510.5.4 item 6).
- The contract, invoices and proof of payment.
Send one dated, written request and keep a copy. If the installer has closed down, note that in your file and move on.

Bring in a new contractor
- Ask for a site assessment first. A new contractor should inspect what is installed and test it before quoting a fixed price to finish.
- Check credentials. The designer and lead installer need an FCC general radio operator license and in-building system training at minimum (IFC 2021 510.5.3). In Broward, only a licensed electrical, fire alarm or BDA contractor can contract the installation (BORA ERCES Guidelines 1.6).
- Get the scope in writing: who files the change of contractor or new permit, who updates the license holder's consent, and who schedules the fire department.
- Ask who stands behind the old work. Under F.S. 553.79(16)(a)1, the new contractor answers only for its own work, so decide with them what must be redone.
- Get at least two bids on the same scope if time allows.
Re-test before you accept the job
The system is not done until it passes the acceptance test on every floor, with each floor divided into 20 test areas (IFC 2021 510.5.4). The fire department usually witnesses it. Only after that, and after the permit is closed, should you make the final payment. Then put the annual test on the calendar (IFC 2021 510.6.1). For how the tests work, see BDA system testing.
If a fire marshal deadline is running while all this happens, tell the fire marshal in writing what went wrong and your new dates. See the fire marshal ordered ERRCS for how to write that reply.
Get help finishing the job
The form below sends your request to up to 3 licensed installers who serve your area. They reach you by email, or by phone only if you choose calls.
Free for owners, boards and managers
Get up to 3 quotes to finish the job
Two minutes. We send your request to installers who work in your county and know your fire marshal.
- Up to 3 licensed installers who serve your area may contact you. Never more than 3.
- By email, or by phone call only if you choose calls below.
- No texts, no robocalls, and we never sell your request to a marketing list.
- Owners never pay us. Installers pay ERRCSCheck for the introduction.
- If no installer covers your area, we tell you within 2 business days and send your local requirements instead.
ERRCSCheck is a private company, not a government agency or fire department.
Request received
Thank you. Up to 3 licensed installers who serve your area will contact you, usually within 2 business days.
Next step
Take the board a plan, not just a problem
Ask for up to 3 quotes from vetted installers who serve your area, or start with a one-page brief the board can read before the next meeting. Free for owners, boards and managers. No texts, no cold calls.
Questions people ask
How long before an ERRCS permit expires in Florida?
It depends on the local building code and the office that issued it. Permits commonly lapse when work does not start, or stops, for a set period. Call the permitting office, give the permit number and ask for the exact expiration date and whether an extension is possible. Do not rely on a contractor's guess.
Can a new contractor finish the old contractor's work?
In Florida, a property owner may hire a different appropriately licensed contractor to do the work needed to close a building permit, and that contractor is liable only for its own work, not the original contractor's defects (F.S. 553.79(16)(a)1). Expect the new contractor to inspect and test what is already installed before taking it on.
Do we need the radio license holder's consent again?
Ask the license holder. Consent is required before a booster operates (47 CFR 90.219(b)(1)(i)), and Florida requires it for any new system or change to an existing one (F.S. 633.202(18)(d)). If the new contractor changes the design or equipment, plan on a new or updated consent.
What if we already paid for work that was not done?
That is a contract question for your attorney. Bring the contract, invoices, payment records and every message with the old installer. This page covers the permit and the paperwork, not legal claims.
Sources
Primary documents we read for this page. Rules change; confirm with your fire marshal (AHJ).
- Florida Statutes 2026, section 553.79, Permits; applications; issuance; inspections (subsection (16)), The Florida Senate
- International Fire Code 2021, Section 510 (text as published by the City of Eaton), City of Eaton, reproducing the ICC International Fire Code
- Florida Statutes 2026, section 633.202, subsection (18), The Florida Senate
- 47 CFR 90.219, Use of signal boosters, Electronic Code of Federal Regulations
- BORA ERCES Guidelines, revised 2021-10-14 (archived copy; broward.org blocks automated access), Broward County Board of Rules and Appeals
Related
Something happened with your building's radio coverage. Start here.
Plain next steps for owners, condo boards and managers: failed coverage test, fire marshal order, expired permit, CO on hold or a board that needs quotes.
The fire marshal says your building must install ERRCS. Here is your plan.
The fire marshal wants a BDA or ERRCS system installed. How to confirm it applies, test first, count your Florida year, get consent and a permit.
Your building failed a radio coverage test. Here is what to do next.
Failed an ERRCS signal or grid test? What the result means, the fix options from antennas to a full BDA, how long Florida gives you, and how to get bids.
The ERRCS project, step by step
The five steps of an ERRCS project, from checking the rule to the annual test: who does each one, what it produces, how long it takes and what goes wrong.