Washington · county · ERRCS / BDA requirements

ERRCS and BDA requirements in Pierce County, Washington

In the area Pierce County's Fire Prevention Bureau serves, every new building must prove adequate emergency responder radio coverage before a certificate of occupancy. If testing shows coverage is deficient, an ERRCS must be installed under the handout and IFC Section 510. The handout applies to projects requiring coverage under Pierce County Code 17C.60.195.

Last verified Updated Confidence medium2 sourcesChangelog

Mid-rise and high-rise buildings from street level.

Confidence medium

Last verified

Check this building

Guidance, not engineering advice. Rules on this page come from the documents listed under Sources. Confirm with Pierce County Fire Prevention Bureau (Department of Emergency Management) before you design, permit or test a system.

Who must comply

State rules apply here too. See Washington statewide rules.

RuleEffectCitationSource
Before a certificate of occupancy, all new buildings must provide proof of adequate emergency responder radio coverage, by testing under IFC 510.5.3 or a field demonstration of clear two-way communication. If coverage is inadequate, an ERRCS must be installed.Must meetPierce County ERRCS Handout, RequirementsPierce County Department of Emergency Management, Fire Prevention Bureau
TriggerPublished value
Minimum building sizeNot published; confirm with the fire marshal
Minimum storiesNot published; confirm with the fire marshal
Height triggerNot published; confirm with the fire marshal
Below-grade areasNot published; confirm with the fire marshal
Building types namedNot published; confirm with the fire marshal
Existing buildings must retrofitNot published; confirm with the fire marshal
Compliance deadlineNot published; confirm with the fire marshal

We have not read Pierce County Code 17C.60.195, which sets which projects are in scope. Washington's state rules for existing buildings still apply.

questions, about a minute

Free. Runs in your browser; nothing is sent until you ask for quotes. The full checker asks a few more questions.

RequirementValue
Minimum downlink signal-95 dBm
Minimum uplink signalNot published; confirm with the fire marshal
Delivered audio quality (DAQ)3.4
Coverage, general areasNot published; confirm with the fire marshal
Coverage, critical areas99% of floor area
Critical areas namedFire command centers, Fire pump and controller rooms, Exit stairs, Exit passageways, Elevator lobbies, Standpipe cabinets, Interior sprinkler valve or sprinkler and alarm control rooms, Other Critical Communication Areas the fire marshal identifies
Public safety radio bandsPierce County 700 MHz P25; City of Puyallup 800 MHz where those agencies respond

The handout requires 99% coverage at not less than -95 dBm and DAQ 3.4 in critical areas, and design to DAQ 3.4 overall; it does not print a general-area percentage. Only Class A signal boosters are approved; Class B devices are not. The uplink signal at the donor site must be no greater than -75 dBm, measured by Pierce County Radio Communications before the DAQ coverage test.

A firefighter keys a shoulder microphone in a stairwell.
Coverage is measured where firefighters work: stairwells, corridors and below grade.

How coverage is tested

One floor, 20 squares, a radio check in each

Illustration
The coverage test grid on one floorA floor plan divided into 20 equal test areas in a 5 by 4 grid, with a test spot at the center of each. The stair and the elevator lobby are marked as critical areas. Nineteen areas pass and one fails, so this floor passes.StairElevators1234
  1. 20 test areas per floorEach floor is divided into a grid of 20 roughly equal areas.IFC 2021 510.5.4
  2. One test spot per areaA spot near the center stands for the whole area. No extra spots after it is chosen.
  3. One failed area is allowedMore than one failed area fails the floor. With exactly two, the floor may be re-divided into 40 areas, and up to two non-adjacent failures are allowed.IFC 2021 510.5.4
  4. Critical areas count moreTypical model-code targets: 95 percent of all areas and 99 percent of critical areas such as stairs and elevator lobbies. Your fire marshal sets the numbers that apply to you.IFC 2021 510.4.1

Illustration: 19 of 20 areas pass, so this floor passes. Some fire departments use other numbers; Miami-Dade, for example, stops an acceptance test below 90 percent of general areas.

How the model fire code's grid test decides whether a floor has enough radio coverage.Source: IFC 2021 510.4.1, 510.5.4. Typical model-code values; your AHJ sets them.

Testing

TestWhat the source saysSource
Acceptance testThe installer pre-tests and sends floor plans with grid overlays, grid-by-grid inbound and outbound results and a certification to the ERRC program. The fire marshal then witnesses an on-site test: visual inspection, 1 hour of operation on normal, battery and backup power, signal and DAQ checks in selected areas and every critical area, and at least five random trouble signals. Any failure fails the whole system.Pierce County ERRCS Handout, ERRCS Testing
Annual testNot published in the documents we read; confirm with the fire marshal.None found
Five-year testNot published in the documents we read; confirm with the fire marshal.None found
Coverage assessment intervalNot published in the documents we read; confirm with the fire marshal.None found
An amplifier enclosure and battery cabinet in an equipment closet.
The amplifier, its battery and its alarms are part of every acceptance and annual test.

Maintenance and monitoring

  • Primary power on a dedicated circuit; standby power per IFC 510.4.2.3.
  • Supervisory signals include low battery when 70% of the 24-hour operating capacity is used, and low generator fuel where a generator is used.
  • A dedicated monitoring panel in the fire command center (or approved location) shows seven labeled conditions.
  • Pierce County may have any device shut off if it is suspected of interfering with the 700 MHz P25 system until it is repaired and approved.

Source: ERRCS Handout, Steps to Success for ERRC Compliance (effective 11/15/2022)

Permit and inspection process

  1. Contact Pierce County Radio for the ERRC Request for Authorization (the licensee's permission to rebroadcast its frequencies). Handout, Steps to Success 1
  2. Apply for a permit from the Fire Prevention Bureau with the site plan, floor plans, equipment listings, personnel qualifications, the Request for Authorization and an attestation. Handout, Steps 2 and Permitting
  3. Install after approval, pre-test, and send the pre-test results to [email protected]. Handout, Steps 3-5
  4. Schedule the Fire Prevention Bureau inspection and witnessed acceptance test. A re-inspection fee applies after two inspections. Handout, Step 6 and ERRCS Testing

Frequency information and tower coordinates are provided case by case depending on which agencies respond to the address.

A technician and a manager review a building drawing.
Most fire departments review drawings before an installer can start.

Codes and standards referenced

Code or standardEditionSource
Pierce County Code 17C.60.195 (scope; not read by us)Not published; confirm with the fire marshals1
International Fire Code Section 510 (as referenced)Not published; confirm with the fire marshals1

Notes

Medium confidence: the handout is from 2022 and we did not read the county ordinance it points to. The county site blocks automated requests, so we read an Internet Archive copy; the live link is listed first.

Next step

Take the board a plan, not just a problem

Ask for up to 3 quotes from vetted installers who serve your area, or start with a one-page brief the board can read before the next meeting. Free for owners, boards and managers. No texts, no cold calls.

Questions people ask

Can I use a Class B signal booster in Pierce County?

No. The handout says ERRCS devices must be Class A rated, and Class B devices will not be approved by Pierce County (Pierce County ERRCS Handout, Radio Requirements).

Sources

Primary documents we read for this page. Rules change; confirm with your fire marshal (AHJ).

  1. ERRCS Handout, Steps to Success for ERRC Compliance (effective 11/15/2022), Pierce County Department of Emergency Management, Fire Prevention BureauVerified October 25, 2026 · ahj document
  2. Internet Archive copy of the Pierce County ERRCS Handout, captured 2026-04-30 (the county site blocks automated requests), Internet ArchiveVerified October 25, 2026 · other