Washington · ERRCS / BDA requirements

ERRCS requirements in Washington

Washington's state fire code requires approved in-building emergency responder communications enhancement (ERCES) coverage in all new buildings, based on the public safety signal measured outside. Existing buildings other than Group R-3 without approved coverage must add it when a wired system cannot be repaired or is replaced, or within a time frame the local adopting authority sets.

Last verified Updated Confidence high2 sourcesChangelog

Mid-rise and high-rise buildings from street level.

Confidence high

Last verified

Check this building

Guidance, not engineering advice. Rules on this page come from the documents listed under Sources. Confirm with your local fire code official (the authority having jurisdiction) before you design, permit or test a system.

Local fire marshals in Washington

Each local AHJ sets its own signal levels and permit steps within the state rules.

JurisdictionTypeDownlink signalConfidenceLast verified
Pierce CountyCounty-95 dBmmediumOct 25, 2026
SeattleCityNot published; confirm with the fire marshalmediumOct 25, 2026

Who must comply

RuleEffectCitationSource
Approved in-building ERCES coverage must be provided in all new buildings, based on existing public safety signal levels at the building exterior. Exceptions: an approved wired system, or the fire code official finds coverage is not needed.Must meetWAC 51-54A-0510, Section 510.1Washington State Legislature
Section 1103.2 applies to existing buildings other than Group R-3.Not requiredWAC 51-54A-1103, Section 1103.2Washington State Legislature
Existing buildings without approved coverage must add it where an existing wired communication system cannot be repaired or is being replaced, or within a time frame set by the local adopting authority, unless the fire code official finds it is not needed.AHJ may requireWAC 51-54A-1103, Section 1103.2Washington State Legislature
TriggerPublished value
Minimum building sizeNot published; confirm with the fire marshal
Minimum storiesNot published; confirm with the fire marshal
Height triggerNot published; confirm with the fire marshal
Below-grade areasNot published; confirm with the fire marshal
Building types namedNot published; confirm with the fire marshal
Existing buildings must retrofitYes
Compliance deadlineNot published; confirm with the fire marshal

Local fire codes in Washington (for example Seattle's) add their own amendments and thresholds. Exceptions in the state text: an approved wired communication system, a fire code official finding that coverage is not needed, or an automatically activated system where a system would disrupt operations.

questions, about a minute

Free. Runs in your browser; nothing is sent until you ask for quotes. The full checker asks a few more questions.

RequirementValue
Minimum downlink signal-95 dBm
Minimum uplink signalNot published; confirm with the fire marshal
Delivered audio quality (DAQ)3.0
Coverage, general areas95% of floor area
Coverage, critical areas99% of floor area
Critical areas namedAreas designated as critical by the fire code official
Public safety radio bandsNot published; confirm with the fire marshal

Inbound signal of at least -95 dBm in 95% of the coverage area and 99% of critical areas, with DAQ 3.0 or equivalent SINR. Standby power: 12 hours at 100% capacity (dedicated batteries, or 2-hour batteries plus generator). Equipment listed to UL 2524.

A firefighter keys a shoulder microphone in a stairwell.
Coverage is measured where firefighters work: stairwells, corridors and below grade.

How coverage is tested

One floor, 20 squares, a radio check in each

Illustration
The coverage test grid on one floorA floor plan divided into 20 equal test areas in a 5 by 4 grid, with a test spot at the center of each. The stair and the elevator lobby are marked as critical areas. Nineteen areas pass and one fails, so this floor passes.StairElevators1234
  1. 20 test areas per floorEach floor is divided into a grid of 20 roughly equal areas.IFC 2021 510.5.4
  2. One test spot per areaA spot near the center stands for the whole area. No extra spots after it is chosen.
  3. One failed area is allowedMore than one failed area fails the floor. With exactly two, the floor may be re-divided into 40 areas, and up to two non-adjacent failures are allowed.IFC 2021 510.5.4
  4. Critical areas count moreTypical model-code targets: 95 percent of all areas and 99 percent of critical areas such as stairs and elevator lobbies. Your fire marshal sets the numbers that apply to you.IFC 2021 510.4.1

Illustration: 19 of 20 areas pass, so this floor passes. Some fire departments use other numbers; Miami-Dade, for example, stops an acceptance test below 90 percent of general areas.

How the model fire code's grid test decides whether a floor has enough radio coverage.Source: IFC 2021 510.4.1, 510.5.4. Typical model-code values; your AHJ sets them.

Testing

TestWhat the source saysSource
Acceptance testAfter installation the owner has the system tested to show two-way coverage on each floor meets Section 510.4.1, using grid testing with a calibrated spectrum analyzer and talk-back tests scored on DAQ (3 or higher passes), including each critical area and each stairwell landing.WAC 51-54A-0510, Section 510.5.4
Annual testThe owner has the system inspected and tested annually and after structural changes: coverage test, booster gain check, 1-hour battery load test, component checks and a fire alarm supervision test, with a report to the fire code official. Annual testing is not required inside Group R dwelling units.WAC 51-54A-0510, Section 510.6.1
Five-year testSection 510.6.1.1 lets a shorter alternative annual coverage test be used when the acceptance documentation, or the most recent full five-year test results for systems older than six years, are available. The text refers to a full five-year test but we have not found where it sets that test's schedule; confirm with the fire marshal.WAC 51-54A-0510, Section 510.6.1.1
Coverage assessment intervalNot published in the documents we read; confirm with the fire marshal.None found
An amplifier enclosure and battery cabinet in an equipment closet.
The amplifier, its battery and its alarms are part of every acceptance and annual test.

Permit and inspection process

  1. A construction permit is required to install or modify the system; maintenance is not a modification. WAC 51-54A-0510, Section 510.3
  2. The system type is determined by the fire code official and the frequency license holder. WAC 51-54A-0510, Section 510.1

Designers and lead acceptance testers need an FCC general radio telephone operator license plus in-building system training (Section 510.5.3).

A technician and a manager review a building drawing.
Most fire departments review drawings before an installer can start.

Codes and standards referenced

Code or standardEditionSource
International Fire Code Section 510 as amended by WAC 51-54A-0510Effective 3/16/24s1
IFC Section 1103.2 as amended by WAC 51-54A-1103Effective 3/15/24s2
NFPA 1221 (named for design and installation)Not published; confirm with the fire marshals1

Notes

Read in the Washington Administrative Code on the Legislature's site. These sections amend the International Fire Code; the unamended IFC text is not reproduced here.

Next step

Take the board a plan, not just a problem

Ask for up to 3 quotes from vetted installers who serve your area, or start with a one-page brief the board can read before the next meeting. Free for owners, boards and managers. No texts, no cold calls.

Questions people ask

Does Washington require ERRCS in every new building?

The state fire code requires approved in-building coverage in all new buildings, measured against the public safety signal outside. A system is needed only where the building cannot meet the signal levels, and the fire code official can find coverage is not needed (WAC 51-54A-0510, 510.1).

Sources

Primary documents we read for this page. Rules change; confirm with your fire marshal (AHJ).

Get up to 3 quotesCheck this building