ERRCS and BDA requirements in Houston, Texas

Houston's construction code requires emergency responder communication coverage in all buildings. A building is exempt only if it has no basement, is three stories or less, and has 50,000 sq ft or less of total area. New buildings, remodels and lease buildouts must document compliance.

Last verified Updated Confidence high2 sourcesChangelog

Mid-rise and high-rise buildings from street level.

Confidence high

Last verified

Check this building

Guidance, not engineering advice. Rules on this page come from the documents listed under Sources. Confirm with City of Houston Building Code Enforcement and Houston Fire Department before you design, permit or test a system.

Who must comply

RuleEffectCitationSource
Buildings without basements, three stories or less in height, and with an aggregate total building area of 50,000 sq ft or less are exempt.Not requiredHouston ERCC Guideline (CE-1350), ExemptionCity of Houston, Houston Permitting Center
New buildings must comply with the ERCC provisions. Before any BDA is installed, a test (with Form CE-1386) shows whether the building already has the required coverage or needs a signal enhancing system.Must meetHouston ERCC Guideline (CE-1350), Purpose and New ConstructionCity of Houston, Houston Permitting Center
Plans for remodels and lease buildouts of existing facilities must document ERCC compliance in the code analysis sheet. Existing facilities with previously authorized wired systems maintain them under the original code of record and Chapter 11.AHJ may requireHouston ERCC Guideline (CE-1350), Existing FacilitiesCity of Houston, Houston Permitting Center
With prior approval of the building official and fire code official, a wired communication system (Section 907.2.13.2) may be used in new construction instead of radio coverage.NoteHouston ERCC Guideline (CE-1350), NoteCity of Houston, Houston Permitting Center
TriggerPublished value
Minimum building sizeNot published; confirm with the fire marshal
Minimum storiesNot published; confirm with the fire marshal
Height triggerNot published; confirm with the fire marshal
Below-grade areasTrue
Building types namedNot published; confirm with the fire marshal
Existing buildings must retrofitNot published; confirm with the fire marshal
Compliance deadlineNot published; confirm with the fire marshal

Houston calls it ERCC (Emergency Responder Communication Coverage). The guideline does not set a deadline for existing buildings without remodel work.

questions, about a minute

Free. Runs in your browser; nothing is sent until you ask for quotes. The full checker asks a few more questions.

RequirementValue
Minimum downlink signalNot published; confirm with the fire marshal
Minimum uplink signalNot published; confirm with the fire marshal
Delivered audio quality (DAQ)Not published; confirm with the fire marshal
Coverage, general areasNot published; confirm with the fire marshal
Coverage, critical areasNot published; confirm with the fire marshal
Critical areas namedNot published; confirm with the fire marshal
Public safety radio bandsNot published; confirm with the fire marshal

The guideline does not print signal levels. Frequencies for a specific site come from City of Houston HITS Radio Communication Services and the Harris County Radio Network Operation Center (RNOC); loaner radios are available for testing.

A firefighter keys a shoulder microphone in a stairwell.
Coverage is measured where firefighters work: stairwells, corridors and below grade.

How coverage is tested

One floor, 20 squares, a radio check in each

Illustration
The coverage test grid on one floorA floor plan divided into 20 equal test areas in a 5 by 4 grid, with a test spot at the center of each. The stair and the elevator lobby are marked as critical areas. Nineteen areas pass and one fails, so this floor passes.StairElevators1234
  1. 20 test areas per floorEach floor is divided into a grid of 20 roughly equal areas.IFC 2021 510.5.4
  2. One test spot per areaA spot near the center stands for the whole area. No extra spots after it is chosen.
  3. One failed area is allowedMore than one failed area fails the floor. With exactly two, the floor may be re-divided into 40 areas, and up to two non-adjacent failures are allowed.IFC 2021 510.5.4
  4. Critical areas count moreTypical model-code targets: 95 percent of all areas and 99 percent of critical areas such as stairs and elevator lobbies. Your fire marshal sets the numbers that apply to you.IFC 2021 510.4.1

Illustration: 19 of 20 areas pass, so this floor passes. Some fire departments use other numbers; Miami-Dade, for example, stops an acceptance test below 90 percent of general areas.

How the model fire code's grid test decides whether a floor has enough radio coverage.Source: IFC 2021 510.4.1, 510.5.4. Typical model-code values; your AHJ sets them.

Testing

TestWhat the source saysSource
Acceptance testBefore the certificate of occupancy or final inspection, the building is tested by a City of Houston registered ERCC third-party special inspector, who also inspects the installation and completes Form CE-1385.Houston ERCC Guideline (CE-1350), Post Installation Testing
Annual testNot published in the documents we read; confirm with the fire marshal.None found
Five-year testNot published in the documents we read; confirm with the fire marshal.None found
Coverage assessment intervalNot published in the documents we read; confirm with the fire marshal.None found
An amplifier enclosure and battery cabinet in an equipment closet.
The amplifier, its battery and its alarms are part of every acceptance and annual test.

Permit and inspection process

  1. Test the building before installing any BDA and submit the test with Form CE-1386. CE-1350, New Construction: Tests
  2. If a system is needed, submit ERCC plans designed, sealed, signed and dated by a Texas Professional Engineer, either with the construction documents or as a deferred submittal (Form CE-1086). CE-1350, Plan Review Submittal Process
  3. Exterior towers or equipment need Texas PE-sealed structural and anchorage details for Houston wind loads. CE-1350, Deferred Submittal ERCC Plan Review
  4. After installation, a registered ERCC special inspector tests and inspects the system and submits Form CE-1385 to [email protected]. CE-1350, Post Installation Testing; Submittal of Reports

Installation and special inspection testing may be done by a trained Texas PE or by an FCC-licensed General Radio Telephone Operator registered with the City as an ERCC special inspector, with in-building radio system certification.

A technician and a manager review a building drawing.
Most fire departments review drawings before an installer can start.

Codes and standards referenced

Code or standardEditionSource
Houston Fire Code Section 510 and Houston Building Code Section 918 (current adopted editions)Not published; confirm with the fire marshals1
Houston Fire Code Chapter 11 (existing facilities)Not published; confirm with the fire marshals1

Notes

Read in the July 2025 revision of Form CE-1350. The city site blocks automated requests, so we read an Internet Archive copy of the same file; the live link is listed first.

Next step

Take the board a plan, not just a problem

Ask for up to 3 quotes from vetted installers who serve your area, or start with a one-page brief the board can read before the next meeting. Free for owners, boards and managers. No texts, no cold calls.

Questions people ask

Is my Houston building exempt from ERCC?

Only if all three are true: no basement, three stories or less, and 50,000 sq ft or less of total building area (Houston ERCC Guideline, Exemption).

Who must design an ERCC system in Houston?

A Texas Professional Engineer with appropriate training; plans must be sealed, signed and dated (Houston ERCC Guideline, Minimum Qualifications).

Sources

Primary documents we read for this page. Rules change; confirm with your fire marshal (AHJ).