For property and association managers
An ERRCS notice landed on your desk. Here is your first week.
The fire marshal wants proof that firefighters' radios work inside your building. You are the one who has to turn that into a plan the board can approve. Here is the order of work, with the rule behind each step.

Your first week after a notice
Treat the notice like any other code item with a date on it. The work in week one is mostly paper and phone calls.
| Day | Task | Why it matters |
|---|---|---|
| Day 1 | Copy the notice. Note the code section, the deadline, the inspector's contact and exactly what is asked for (a test, a permit application, a working system or a report) | The date and the ask on the notice control what happens next |
| Day 1 | Tell the board president, in writing, with the deadline | Boards need time to meet, vote and fund |
| Day 2 | Pull every fire marshal letter, old test report, permit and drawing you can find | Prior reports can show whether a system was ever accepted |
| Day 2 | Run the building through the checker | It applies published exemptions and cites the source for each line |
| Day 3 | Call the fire department contact. Ask what will satisfy the notice, and whether it publishes technical criteria | The fire code official keeps a document with frequencies and design requirements (IFC 2021 510.4.2.2) |
| Day 4 | Book a signal test or survey | You cannot size a fix without measuring, and some cities require a test before any amplifier goes in (Houston CE-1350) |
| Day 5 | Request comparable bids, or up to 3 quotes through us | Bids take time; start them while the test is scheduled |
In Florida, a required retrofit after the 2024 and 2025 statutory dates gets at least one year from the notice of code violation (F.S. 633.202(18)(g)). Do not plan to use all of it. Testing, design, the licensee's consent, permits and the acceptance test each take their own time.

After a notice
Six steps from the letter to a closed violation
- Read the noticeWrite down the code section, the deadline, the contact and what it asks for.
- Check the ruleRun the checker for your building and look for a published exemption.
- Get a signal testYou cannot size a fix without measuring floor by floor.IFC 2021 510.4.2.2
- Hire qualified peopleFCC general radio operator license and in-building training, at minimum.IFC 2021 510.5.3
- Consent, permit, install, testRadio licensee's consent, a permit, then the acceptance test.47 CFR 90.219(b)(1)(i); IFC 2021 510.3, 510.5.4
- Keep it compliantAn annual test and a report to the fire department, records kept on site.IFC 2021 510.6.1
In Florida, a required retrofit after the statutory dates gets at least 1 year from the notice of code violation (F.S. 633.202(18)(g)). Elsewhere, the date on your notice controls.
Your notice
How long do we have?
Every date here comes from the statute or rule cited under it.
In Florida, after the fire marshal issues a notice of code violation, the owner gets at least 1 year to complete a required retrofit. The date written on your notice controls; it may give you more. F.S. 633.202(18)(g)
Briefing the board
Most board members have never heard the term. Give them the short version first: the fire code requires that firefighters' radios work inside the building, and the fire marshal wants proof or a fix by a date.
Then bring four things to the meeting:
- The notice and its deadline, with the date counted out in months.
- The rule and its citation. In Florida that is F.S. 633.202(18); everywhere, Section 510 of the International Fire Code is the model.
- What you know so far, including whether the checker found an exemption and when the signal test is booked.
- A decision to ask for: approval to spend on the test, and authority to collect bids.
The Board Brief prints all of this on one page, with six questions for installers. Board members who want more can read the plain-English page for condo boards.
Take this to your board
Make a one-page board brief
Plain English, the rule for your building with its citation, the deadlines, sourced cost figures, six questions to ask installers and a QR code for quotes. Print it or save it as a PDF.
- Free, and nothing is stored
- Fits on one letter-size page
- Every rule and figure cites its source
Getting comparable bids
Bids only compare when they cover the same scope. Ask every bidder to price against the same signal test report and to break the quote into lines.
| Ask each bidder for | Rule behind it |
|---|---|
| The signal test or survey their design is based on | IFC 2021 510.4.1 (coverage is measured, not assumed) |
| Design to the fire department's technical criteria | IFC 2021 510.4.2.2 |
| Standby battery sized to the code (12 hours at full capacity in the model code; some cities require more) | IFC 2021 510.4.2.3 |
| Permit and plan review handled by the installer | IFC 2021 510.3 |
| Getting and keeping the radio licensee's written consent | 47 CFR 90.219(b)(1)(i); F.S. 633.202(18)(d) |
| The acceptance test, and who performs it | IFC 2021 510.5.4 |
| Proof of an FCC general radio operator license and in-building system training for the designer and lead installer | IFC 2021 510.5.3 |
| A price for the first annual test and a service agreement | IFC 2021 510.6.1 |
Our BDA system cost page lists what a complete quote includes, line by line. When you request quotes through ERRCSCheck, the request goes to up to 3 vetted installers who serve your area. We send no texts and make no cold calls.

Budgeting for the owners
Owners will ask "how much" before anything else. Be honest that nobody can say until the test is done. What you can share is sourced:
- Reported high-rise figures. In coverage of Fort Lauderdale's citations of 69 high-rises, systems were reported to cost "$250,000 or more", with $200,000 and $275,000 cited for specific buildings; a retired fire chief worked out about $1,000 per owner in a 250-unit condo and about $10,000 per owner with 25 owners (Sun Sentinel via Firehouse, November 2025). One city's high-rise data, not a typical price.
- Fire department fees. Miami-Dade charges $281.48 per inspector per hour for the signal verification and acceptance test, $98.46 for a first or second re-inspection and $194.44 for a third or later one (Implementing Order 04-123, effective 10/01/2025). Check your own department's schedule.
- Costs that repeat. A test every year and after structural changes (IFC 2021 510.6.1); in Florida, a coverage re-assessment no more often than every 3 years for high-rises and buildings over 12,000 sq ft, or 5 years for others, with exceptions (F.S. 633.202(18)(c)2); and changes at the owner's expense if radio frequencies change (IFC 2021 510.6.2), with at least 180 days' notice in Florida (F.S. 633.202(18)(f)).
How the association funds the work, and how it is shared with unit owners, is a question for the association's attorney. Our sister site keeps a fuller cost guide for building managers.
The full budget
What an owner pays for, and when
- Before you buySignal test or benchmark survey; engineering design, sometimes a licensed engineer.IFC 2021 510.4.2.7; Houston CE-1350
- InstallEquipment, antennas, cable, fire-rated pathways, batteries, monitoring; permit and plan review; acceptance test.IFC 2021 510.3 to 510.5.4
- Every yearAnnual inspection and test, plus a report to the fire department.IFC 2021 510.6.1
- As neededRepairs within local deadlines; changes when frequencies change; a retest after structural changes.IFC 2021 510.6.1, 510.6.2
- Florida onlyA coverage re-assessment no more than every 3 or 5 years, depending on the building.F.S. 633.202(18)(c)2
Sourced figures only
What it may cost
We print a price only when we can trace it to a published record. Each figure links to its source.
Reported high-rise figures, Fort Lauderdale
Source: Fort Lauderdale cites 69 high-rises with weak radio signals, South Florida Sun-Sentinel (Susannah Bryan), republished by Firehouse, Nov. 7, 2025. These are one city's high-rise data points, not a typical price.
$1,000 per unit if split equally
- $1,000 per owner at $250,000 with 250 owners (a retired fire chief quoted in the article).
- $10,000 per owner at $250,000 with 25 owners (a retired fire chief quoted in the article).
An equal split is arithmetic, not advice. How an association shares costs depends on its governing documents and state law; ask the association's attorney.
We have not found a verifiable published figure for smaller buildings. Get at least three written quotes.
Every cost the rules create
| When | What you pay for | Required by |
|---|---|---|
| Before you buy | Signal test or benchmark survey | Houston CE-1350 (test before any BDA); Phoenix policy (benchmark RF test) |
| Before you buy | Engineering design; some cities require a licensed engineer | IFC 2021 510.4.2.7; Houston CE-1350 (Texas PE); Phoenix policy (Arizona PE certificate) |
| Install | Equipment, antennas, cable, fire-rated pathways, batteries, monitoring | IFC 2021 510.4 to 510.4.2.8 |
| Install | Construction permit and plan review | IFC 2021 510.3 |
| Install | Acceptance test, sometimes by an independent third party | IFC 2021 510.5.4; Palo Alto 510.5.3 |
| Every year | Annual inspection and test, plus a report to the fire department | IFC 2021 510.6.1 |
| As needed | Repairs within local deadlines | LAFD Requirement #105 (evaluation in 24 hours, repair in 5 working days for service-affecting failures; approved 8/7/2018, confirm the current version with LAFD) |
| As needed | Changes when frequencies change | IFC 2021 510.6.2 (owner's expense); in Florida, at least 180 days' notice, F.S. 633.202(18)(f) |
| As needed | Retest after structural changes | IFC 2021 510.6.1 |
| Florida only | Coverage re-assessment no more than every 3 or 5 years, depending on the building | F.S. 633.202(18)(c)2 |
No dollar amounts here on purpose: they depend on your building. Ask each installer to price these lines separately.
Published fire department fees
| Fee | Fire department | Amount | Effective |
|---|---|---|---|
| Signal strength verification and system acceptance test (per inspector per hour) | Miami-Dade County | $281.48 | Oct 1, 2025 |
| Re-acceptance test for existing systems | Miami-Dade County | $311.59 | Oct 1, 2025 |
| Equipment installation inspection, 1 to 6 devices | Miami-Dade County | $210.63 | Oct 1, 2025 |
| Equipment installation inspection, 7 to 100 devices | Miami-Dade County | $351.47 | Oct 1, 2025 |
| Each device over 100 (each device over 100) | Miami-Dade County | $2.00 | Oct 1, 2025 |
| First or second re-inspection of a fire safety system | Miami-Dade County | $98.46 | Oct 1, 2025 |
| Third or later re-inspection | Miami-Dade County | $194.44 | Oct 1, 2025 |
| Plan review, bi-directional amplifier | Fort Myers Beach Fire District | $376.00 | Sep 1, 2023 |
| Bi-directional amplifier acceptance testing | Fort Myers Beach Fire District | $188.00 | Sep 1, 2023 |
| Radio signal testing | Fort Myers Beach Fire District | $50.00 | Sep 1, 2023 |
Official fees, not vendor prices. Miami-Dade lists "no contractor or unable to gain access on inspector's arrival" among the reasons a re-inspection is charged. Check your own fire department's schedule.
Quotes go to up to 3 vetted installers who serve your area. No texts, no cold calls.
Keeping it compliant
The system is not done when it passes. From then on, it belongs on your maintenance calendar.
- Test every year, and after structural changes, with a report to the fire department (IFC 2021 510.6.1). BDACheck sends free test reminders and keeps a test log for the building.
- Keep the acceptance report and amplifier gain values. If they are lost, the owner must rerun the acceptance test (IFC 2021 510.5.4 item 6).
- Keep the licensee's consent in a recordable format (47 CFR 90.219(b)(1)(i)).
- Watch for changes. New windows, new walls and new floors can change the signal, which is why the code asks for a test after structural changes (IFC 2021 510.6.1).
- Let the fire department test. The agency may field test the system at any reasonable time (IFC 2021 510.6.4).
The annual inspection guide covers the yearly routine in detail.
This is guidance, not legal or engineering advice. Confirm with your fire marshal (AHJ) and the association's attorney.

Next step
Take the board a plan, not just a problem
Ask for up to 3 quotes from vetted installers who serve your area, or start with a one-page brief the board can read before the next meeting. Free for owners, boards and managers. No texts, no cold calls.
Questions people ask
Who is legally responsible, the management company or the association?
The fire code puts the obligation on the building owner (IFC 2021 510.5.4 and 510.6.1). For a condominium that is normally the association acting through its board. What the management contract asks of you is between you and the association; this site does not cover it.
Can I sign the installer contract myself?
That depends on your management agreement and the association's governing documents. Most boards approve a contract of this size by vote. Bring the bids and a one-page summary to the board; the Board Brief is built for that.
The notice gives a date that looks too short. What do I do?
Call the contact on the notice and ask what they need by that date. Often it is a test, a permit application or a plan, not a finished system. In Florida, a required retrofit after the statutory dates gets at least 1 year from the notice of code violation (F.S. 633.202(18)(g)). Get any extension or clarification in writing.
Sources
Primary documents we read for this page. Rules change; confirm with your fire marshal (AHJ).
- Florida Statutes 2026, section 633.202, subsection (18), The Florida Senate
- International Fire Code 2021, Section 510 (text as published by the City of Eaton), City of Eaton, reproducing the ICC International Fire Code
- 47 CFR 90.219, Use of signal boosters, Electronic Code of Federal Regulations
- Fort Lauderdale cites 69 high-rises with weak radio signals (South Florida Sun Sentinel, republished by Firehouse, November 7, 2025), Firehouse
- Implementing Order 04-123: Miami-Dade County Fire Prevention Fee Schedule (effective 10/01/2025), Miami-Dade County
- Emergency Responder Communication Coverage (ERCC) Guideline, Form CE-1350 (revised July 2025), City of Houston
Related
Your building got an ERRCS notice. Here is what it means.
ERRCS in plain English for condo owners and boards: why firefighters need it, the Florida deadlines, reported costs, and what to bring to your next board meeting.
You got a notice about your building's radio coverage. Start here.
A calm first step after a fire marshal notice about ERRCS or emergency radio coverage: what the notice is asking for, what happens next, and who to call first.
What a BDA system costs, part by part
What drives the cost of a BDA system for firefighter radio coverage, which code rules add cost, and one reported high-rise price, with sources.
ERRCS testing and annual inspection for owners
What owners must do to keep an ERRCS compliant every year: when tests are due, where reports go, deadlines by city, records and failed tests.